Digestive Specialists – Shull Road Project Update

Work continues aggressively at the Shull Road location of the future Digestive Specialists’ medical office building.  Exterior masonry is close to completion, and soon the site will be ready for curbing and paving.  Work on the interior of the building includes installation of the ceiling grids, hanging and finishing of drywall, and painting.  Currently, there are ten trades on site working together to complete this project.

Last week’s progress meeting included representatives from six trades as well as the Owner and Architect, ensuring open communications and an understanding of everyone’s roles and responsibilities on the project, which is on target for a year-end completion.