September 20, 2018 / By Donna Reist, Marketing Specialist

Project Update – Rumpke Headquarters

Site work continues on the Rumpke Headquarters project, with all curb work complete. Most of the sidewalks are complete on site with the decorative sidewalks starting soon. Masonry and glazing work continues on the façade of the building. Plumbing and sprinkler work rough-ins are complete inside the building, HVAC and electrical rough-in work continue. Interior finishes have begun on the 3rd floor, including ceilings, flooring, paint, and casework.