September 28, 2018 / By Donna Reist, Marketing Specialist

Project Update – The Residences at Ag47

A lot of progress is happening at Silverton’s latest development!

Exterior:  Façade including windows, masonry, and trim work continues at apartment C.

Shell:  The framing of 3 of the 4 PODs are near completion on the apartment buildings. The framing of the 4th and final POD of the apartment building is scheduled for completion by the beginning of November.  The framing of the 2nd building, identified as Town Home B will start soon.

Interior:  Mechanical and electrical rough-in is near completion, while the start of drywall has begun.

For more information about this development, contact Brian Copfer at 513.774.8400.