February 14, 2019 / By Donna Reist, Marketing Specialist

Ag47 Project Update

In the face of a cold and wet couple of weeks, the crews onsite have persevered.  Site cleanup and grading at the north and east elevations are underway in anticipation of site concrete and curb work.  Exterior brick and fiber cement panel completion for the apartment building is anticipated next week.  Scaffold erection commenced at the first Townhome.

Inside the apartment building, the last of the drywall is being hung with painting occurring in various stages across all Pods.  Initial cleaning and final painting are underway in the first Pods.  Cabinets and countertop installation are proceeding, and the remaining gypcrete pours are scheduled.  Model unit furniture will be delivered next week.  In the Townhomes, exterior window finishes are underway.  With mechanical rough-ins nearing completion, pre-rock and insulation has started.  Drywall stocking is anticipated in the next few weeks.

We are now pre-leasing! Our Community Manager, Robin, and Leasing Specialist, Tiffany, are onsite and taking appointments to view the model apartment homes and townhomes starting Tuesday, February 19th. Please call 513.245.8245 for more information.