April 22, 2019 / By Donna Reist, Marketing Specialist

Project Update – FESTO USA

FESTO 38-week construction update on Mason, OH expansion: Structural steel is approximately 50% complete on Building 2. Progress on Building 3 includes installation of metal panels on the est side of the facility and roofing materials staged for installation. Also for Building 3, slab-on-grade work continues with concrete pouring and finishing.