The construction site at Pratt Wapakoneta is full of activity, including site preparation, construction/erection of concrete wall panels, and setting of structural steel that will connect this 704,000 SF addition to the existing Pratt paper mill plant.

While waiting for the load-bearing concrete wall panels to be erected, structural steel was started in the center of the building to maintain the construction schedule. An on-site concrete batch plant cuts down on delivery time to the job site, allowing the floor slab and wall panel pours to be done in less time.

We are pleased to be working with Schaefer and Choice One Engineering Corp. on this project!